- What is the Green Energy Corridor (GEC)? β Transmission lines and substations built to carry power from renewable energy (RE) sites to the grid and load centres. It builds transmission, not generation.
- Two parts: an intra-state part (InSTS), run by MNRE and built by the states, and an inter-state part (ISTS), built by POWERGRID.
- GEC Phase I (intra-state): 8 states, about 24 GW of RE, 9,700 ckm of lines and 22,600 MVA of substations; estimated cost βΉ10,141.68 crore, with Central Financial Assistance (CFA) of βΉ4,056.67 crore.
- GEC Phase II (intra-state): approved by the CCEA on 6 January 2022; 7 states, about 20 GW of RE, about 10,750 ckm and 27,500 MVA; cost βΉ12,031.33 crore, with CFA at 33% (βΉ3,970.34 crore); to be built over FY 2021-22 to 2025-26.
- GEC Phase II β ISTS for Ladakh: approved on 18 October 2023 to evacuate 13 GW of RE from Pang, Ladakh; cost βΉ20,773.70 crore, with CFA at 40%; target FY 2029-30.
- UPSC Angle: RE integration, energy transition, Centre-State roles in the power sector, and how a transmission scheme is funded.
π GEC Phase I (Intra-State)
- States (8): Andhra Pradesh, Gujarat, Himachal Pradesh, Karnataka, Madhya Pradesh, Maharashtra, Rajasthan and Tamil Nadu.
- Scope: 9,700 ckm of transmission lines and 22,600 MVA of substations to evacuate about 24 GW of RE.
- Cost: βΉ10,141.68 crore; CFA βΉ4,056.67 crore.
- Funding pattern: 40% grant from the Centre (originally from the National Clean Energy Fund), 40% soft loan (KfW, Germany) and 20% state equity.
π GEC Phase II (Intra-State)
- Approval: Cabinet Committee on Economic Affairs (CCEA), 6 January 2022.
- States (7): Gujarat, Himachal Pradesh, Karnataka, Kerala, Rajasthan, Tamil Nadu and Uttar Pradesh.
- Scope: about 10,750 ckm of lines and 27,500 MVA of substations (a 2023 release gives 10,753 ckm and 27,546 MVA), for about 20 GW of RE.
- Cost: βΉ12,031.33 crore, with CFA at 33% (βΉ3,970.34 crore). The CFA offsets intra-state transmission charges, which keeps power costs down for consumers.
- Period: FY 2021-22 to 2025-26. The approval linked it to the target of 450 GW of installed RE capacity by 2030.
π GEC Phase II β Inter-State Transmission for Ladakh
- Background: In his 15 August 2020 speech, the Prime Minister announced a 7.5 GW solar park in Ladakh. MNRE then planned 13 GW of RE with 12 GWh of battery storage (BESS) at Pang.
- Scope: 713 km of lines, including 480 km of HVDC line, plus a 5 GW HVDC terminal at each end, at Pang (Ladakh) and Kaithal (Haryana). The line passes through Himachal Pradesh and Punjab.
- Technology: Voltage Source Converter (VSC)-based HVDC, plus extra high voltage AC lines.
- Implementing agency: POWERGRID, chosen because of the difficult terrain, harsh climate and defence sensitivities.
- Cost and timeline: βΉ20,773.70 crore; CFA at 40% (βΉ8,309.48 crore); target FY 2029-30.
- Local links: to the existing Ladakh grid, and to the Leh-Alusteng-Srinagar line to supply Jammu & Kashmir.
π Who Does What
- MNRE: runs the intra-state GEC scheme and releases the CFA.
- States: their transmission utilities build and own the intra-state lines.
- POWERGRID: builds the inter-state components, including the Ladakh project.
β Progress (Rajya Sabha reply, 9 March 2026)
- GEC-I and GEC-II together cover 10 states: Rajasthan, Karnataka, Andhra Pradesh, Himachal Pradesh, Madhya Pradesh, Kerala, Gujarat, Uttar Pradesh, Maharashtra and Tamil Nadu.
- The two phases are meant to evacuate 44 GW of RE; 26 GW had been integrated.
- An intra-state GEC-III scheme for large-scale RE integration is under consideration.
- RE capacity commissioned was about 263 GW as of January 2026.
- Inter-regional transmission capacity is planned to rise from 120 GW (January 2026) to 168 GW by 2032.
β Phase-wise State Lists
- Only in GEC-I: Andhra Pradesh, Madhya Pradesh, Maharashtra.
- Only in GEC-II: Kerala, Uttar Pradesh.
- In both: Gujarat, Himachal Pradesh, Karnataka, Rajasthan, Tamil Nadu.
π― Green Energy Corridor: Multi-Dimensional Analysis
πΉ Why Transmission Is the Bottleneck
- Location mismatch: The best solar and wind sites (Rajasthan, Gujarat, Ladakh, the southern wind states) are far from the big load centres.
- Timing mismatch: A solar park can be built in a year or two, but transmission lines take longer, mainly because of right-of-way and forest clearances. Without lines, generation is stranded.
- Variability: Solar and wind output changes with weather and time of day, so the grid needs stronger links, storage and flexible resources.
πΉ How the Government Is Responding (PIB, March 2026)
- Planning: GEC and the wider ISTS expansion are planned to integrate over 500 GW of non-fossil capacity by 2030 and over 600 GW by 2032.
- Network growth: Under the National Electricity Plan (Volume-II, Transmission), the 220 kV-and-above network is projected to reach 6.48 lakh ckm, with 2,345 GVA of transformation capacity, by 2031-32.
- Storage: Transmission for 35.6 GW of pumped storage projects has been planned up to 2031-32; about 47 GW of BESS is considered for integration by 2031-32; two Viability Gap Funding schemes support about 43.8 GWh of BESS.
- Regulation: CERC's 2025 amendment to the GNA regulations introduced solar-hour and non-solar-hour connectivity, so the same line can serve solar by day and other sources at other times.
πΉ Federal Dimension
- Electricity is in the Concurrent List (Entry 38, List III). The Centre funds part of the intra-state work through CFA, but states build and own those lines.
- Why the CFA matters: Without it, states hosting RE parks would pass higher intra-state transmission charges on to their consumers, though much of the power may be used elsewhere.
- Inter-state lines such as the Ladakh link fall under the Centre, which is why POWERGRID implements them.
πΉ Challenges & Way Forward
- Right-of-way and clearances: Land compensation disputes and forest and wildlife clearances delay lines, as the extended GEC-I deadlines show.
- Utilisation: Of the 44 GW the two intra-state phases were meant to evacuate, 26 GW was integrated by March 2026. Lines are only useful once the RE capacity they serve is built.
- DISCOM finances: Weak distribution companies delay payments and power purchase agreements, which slows RE capacity addition.
- Ecology: Overhead lines in desert and Himalayan habitats raise wildlife concerns. In Rajasthan and Gujarat, overhead lines in Great Indian Bustard habitat have been the subject of Supreme Court proceedings.
πΉ Mains Answer Framework
- Contextualize: The 500 GW non-fossil target for 2030 and the net-zero goal for 2070.
- Explain the scheme: GEC-I, InSTS GEC-II and the Ladakh ISTS project, with the funding pattern.
- Critically evaluate: Right-of-way delays, under-used capacity, DISCOM finances and ecological trade-offs.
- Way forward: Plan transmission ahead of generation, add storage, speed up clearances and take up GEC-III.
π Case 1: Ladakh 13 GW Project β HVDC in the Himalaya
- Context: Ladakh has strong solar potential but is far from the main load centres and has a small local grid.
- Intervention: A 713 km link, including 480 km of HVDC line, from Pang to Kaithal in Haryana, with 5 GW HVDC terminals at both ends.
- Why HVDC: Long distances, difficult terrain and a large bulk transfer.
- UPSC Link: Energy transition + Border-area development + Strategic infrastructure + Technology choice.
π Case 2: Funding Design β Why CFA Fell from 40% to 33%
- GEC-I: 40% central grant, 40% soft loan from KfW and 20% state equity.
- InSTS GEC-II: CFA cut to 33% of project cost; the rest is for the states to raise.
- Ladakh ISTS: CFA back at 40%, reflecting the project's difficulty and strategic location.
- UPSC Link: Cooperative federalism + Centre-State burden-sharing + External development finance.
Q1. With reference to the Green Energy Corridor (GEC) in India, consider the following statements:
1. The intra-state component is built by the states, while POWERGRID builds the inter-state component.
2. The Intra-State Transmission System GEC Phase-II covers seven states, including Kerala and Uttar Pradesh.
3. Central Financial Assistance under the Intra-State Transmission System GEC Phase-II is 40% of the project cost.
Which of the statements given above are correct?
β Answer: (a) 1 and 2 only
π‘ Explanation: Statement 3 is incorrect: CFA under InSTS GEC-II is 33% (βΉ3,970.34 crore). The 40% rate applies to GEC-I and to the Ladakh inter-state project.
Q2. The Intra-State Transmission System β Green Energy Corridor Phase-II, approved in January 2022, has an estimated cost of about:
β Answer: (b) βΉ12,031 crore
π‘ Explanation: InSTS GEC-II costs βΉ12,031.33 crore. βΉ10,141.68 crore is the GEC-I intra-state cost, and βΉ20,773.70 crore is the Ladakh inter-state project.
Q3. Consider the following pairs about the GEC Phase-II inter-state project for 13 GW of RE in Ladakh:
1. Implementing agency | POWERGRID
2. Point of integration with the National Grid | Kaithal, Haryana
3. Central Financial Assistance | 33% of project cost
How many pairs are correctly matched?
β Answer: (b) Only two
π‘ Explanation: Pairs 1 and 2 are correct. The Ladakh project's CFA is 40% (βΉ8,309.48 crore of βΉ20,773.70 crore); 33% is the intra-state GEC-II rate.
Q4. Which one of the following states is covered by the Intra-State GEC Phase-II but was NOT part of GEC Phase-I?
β Answer: (b) Kerala
π‘ Explanation: Kerala and Uttar Pradesh joined in Phase-II. Maharashtra, Andhra Pradesh and Madhya Pradesh were only in Phase-I.
Q5. According to the Government's March 2026 reply in Parliament, how much renewable energy capacity had been integrated under the intra-state GEC-I and GEC-II, out of the 44 GW planned?
β Answer: (b) About 26 GW
π‘ Explanation: The Ministry of Power's Rajya Sabha reply of 9 March 2026 says the two phases are for evacuating 44 GW of RE, of which 26 GW is integrated.
π Green Energy Corridor in 10 Seconds
- GEC-I (intra-state): 8 states; ~24 GW; 9,700 ckm; βΉ10,141.68 Cr; funded 40% central grant + 40% KfW loan + 20% state equity
- InSTS GEC-II: CCEA 6 Jan 2022; 7 states; ~20 GW; ~10,750 ckm; βΉ12,031.33 Cr; CFA 33%; FY22βFY26
- GEC-II ISTS Ladakh: CCEA 18 Oct 2023; 13 GW; 713 km (480 km HVDC) PangβKaithal; βΉ20,773.70 Cr; CFA 40%; POWERGRID; by FY 2029-30
- Progress (Mar 2026): 26 GW of the 44 GW integrated; GEC-III under consideration
- Roles: MNRE runs the intra-state scheme; states build intra-state lines; POWERGRID builds inter-state lines
- Challenge: Right-of-way, clearances, DISCOM finances, wildlife impacts
π§ Mnemonic: "GEC = 1-2-L"
1 β Phase I: 8 states, 24 GW, 40% grant (+ KfW loan)
2 β Phase II intra-state: 7 states, 20 GW, 33% CFA
L β Ladakh inter-state: 13 GW, HVDC to Kaithal, 40% CFA, POWERGRID
π Prelims Traps to Avoid
- β GEC is transmission-focused, not a generation subsidy (unlike the Solar Park scheme or PM Surya Ghar)
- β Intra-state lines are built by the states, not POWERGRID; POWERGRID builds the inter-state parts
- β CFA is 33% for InSTS GEC-II, not 40% and not 100%
- β InSTS GEC-II was approved in January 2022; the October 2023 approval is the separate Ladakh ISTS project
- β Kerala and Uttar Pradesh are in Phase-II only
π― Mains One-Liners
- "Renewable capacity is only as useful as the transmission that carries it; GEC builds that link"
- "Central Financial Assistance keeps intra-state transmission charges from falling on consumers in RE-host states"
- "The Ladakh HVDC link shows transmission as strategic infrastructure, not just a utility asset"
- "Way Forward: plan transmission ahead of generation, pair it with storage, and speed up right-of-way clearances"